Sr No | BENEFICIARY | NAME OF WORK | NO OF BRIDGES COMPLETED |
1 | Central Railway | Govandi – Extension of FOB towards west side | 1 |
2 | Central Railway | Construction Fabrication and Errection of FOB at Nahur Station | 1 |
3 | Central Railway | Foot Over Bridge, Elevated Booking office at Kopar station , path way Circulating Area | 2 |
4 | Central Railway | Mumbra – FOB 3.66 m wide towards Kalyan end | 1 |
5 | Mumbai Railway Vikas Corporation | Foot Over Bridge at Dahanu Road, Umroli & Vaitarna for the running of EMU services | 4 |
6 | Central Railway | FOB’s at Vikhroli Station (CST & Thane end) for Kurla Thane PHASE I Project. | 2 |
7 | Central Railway | Bhandup – A) Extension of Kalyan end FOB to connect Platform No 3 & 4 | 1 |
8 | Mumbai Railway Vikas Corporation | Extension of Railway FOB at KM 14.83 ( North of Bandra Platform) and middle FOB | 2 |
9 | Central Railway | FOB & Staircase at Chunnabhatti in connection with laying of Single goods line From Wadala to Kurla | 1 |
10 | Central Railway | A) Kurla -Replacement of Mumbai End FOB B) Tilak Nagar – Provision of New FOB at Mankurd End | 2 |
11 | Central Railway | FOB, COP, Platform and circulating area in Pen – Roha section in Panvel – Pen Roha Doubling Project | 2 |
12 | Mumbai Railway Vikas Corporation | New FOB & Extension of harbour line platform from 9 car to 12 car at BA & STC stations of Western Railway under MTP | 2 |
13 | Mumbai Railway Vikas Corporation | FOB Extension of harbour line platform from 9 car to 12 car at Mahim station of Western Railway ” | 2 |
14 | Mumbai Railway Vikas Corporation | Trespassing Control measures including Deck at Borivali & Kandivali and provision of Escalators | 3 |
15 | Mumbai Railway Vikas Corporation | Tilak Nagar Foot Over Bridge at North end | 1 |
16 | Mumbai Railway Vikas Corporation | FOB at Vadala Road & King’s Circle stations and P.Way works at Vadala Road station | 2 |
17 | Central Railway | Construction of a new FOB and dismantling of CST end FOB at Chunabhatti Station to facilitate BKC connector work of MMRDA. | 1 |
18 | Mumbai Railway Vikas Corporation | FOB at Oshiwara including elevated booking office in connection with provision of new station at Oshiwara | 1 |
19 | Mumbai Railway Vikas Corporation | Deck at JOS (South) along with elevated booking offices (SW&SE) | 2 |
20 | Central Railway | Vidhyavihar – Provision of 5m wide FOB along with over head booking office at | 1 |
21 | Western Railway | Borivali- Construction of 12m wide FOB at middle over platform No 1 to 6A and 3m wide FOB over platform No.1 to 4 & 5 at South end | 2 |
22 | Mumbai Railway Vikas Corporation | Elevated Platform at Sandhurst Road stations and P.Way works at CSTM station in connection with ‘running of 12 coach EMU trains on Harbour line’ of Central Railway | 1 |
23 | Mumbai Railway Vikas Corporation | FOB at South end of Tilak Nagar Station | 1 |
24 | Mumbai Railway Vikas Corporation | FOB at Middle of Jogeshwari Station | 1 |
25 | Central Railway | FOB at North end of GTBN Station for wadala 3rd line project | 1 |
26 | Central Railway | Chunabhatti FOB | 1 |
27 | Mumbai Railway Vikas Corporation | Mahim Middle FOB | 1 |
28 | Mumbai Railway Vikas Corporation | Mahalaxmi FOB | 1 |
29 | Mumbai Railway Vikas Corporation | Marine Lines FOB | 1 |
30 | Mumbai Railway Vikas Corporation | Grant Road Middle and south FOB | 2 |
31 | Mumbai Railway Vikas Corporation | Mumbai Central North and South | 2 |
32 | Mumbai Railway Vikas Corporation | FOB at Middle of Charni Road Station | 1 |
33 | Mumbai Railway Vikas Corporation | Mahim Midsection FOB under Midsection Tresspass control works. | 1 |
34 | Mumbai Railway Vikas Corporation | Nallasopara Midesction FOB under Midsection Tresspass control works. | 1 |
35 | Mumbai Railway Vikas Corporation | Andheri FOB under Midsection Tresspass control works | 1 |
36 | Mumbai Railway Vikas Corporation | FOB at Goregaon Middle & South FOB under Midsection TressPass control works | 2 |
37 | Western Railway | FOB at Lower Parel North along with elevated Booking office | 1 |
38 | Western Railway | Bandra Middle FOB | 1 |
39 | Western Railway | Bhayandar FOB | 1 |
40 | Western Railway | FOB’s at North end of Bandra Station | 2 |
41 | Mumbai Railway Vikas Corporation | Vangani FOB | 1 |
42 | Mumbai Railway Vikas Corporation | Vitthalwadi FOB | 1 |
43 | Mumbai Railway Vikas Corporation | Dadar FOB | 1 |
44 | Central Railway | Karjat FOB | 1 |
45 | Mumbai Railway Vikas Corporation | Badlapur FOB | 2 |
46 | Mumbai Railway Vikas Corporation | Kalyan – Karjat FOB | 3 |
47 | Mumbai Railway Vikas Corporation | Mankhurd FOB | 1 |
48 | Mumbai Railway Vikas Corporation | Vashind FOB | 1 |
49 | Mumbai Railway Vikas Corporation | Neral FOB | 1 |
50 | Mumbai Railway Vikas Corporation | Miraroad FOB – Middle | 1 |
51 | Mumbai Railway Vikas Corporation | Construction and commissioning of stabling siding at Juinagar including construction of Bridge, Earthwork, Track linking, Construction of pathway, Ballast supply etc | 1 |
52 | Mumbai Railway Vikas Corporation | Chunabhatti FOB | 1 |
53 | Mumbai Railway Vikas Corporation | Ambivili FOB | 1 |
54 | Mumbai Railway Vikas Corporation | Kalwa FOB | 1 |
| | TOTAL NO OF FOOT OVER BRIDGES COMPLETED = | 76 |